Einstein, Energy and the Price of Getting Time Wrong

Energy TransitionInnovationManagement

Quick Take

The energy transition is as much about timing as it is about technology and capacity. Electricity must be balanced within seconds, demand can be shifted across hours or days, heat can be stored between seasons, and energy infrastructure requires investments that may take decades to pay off.

Recent examples from battery storage, grid congestion and offshore wind demonstrate the financial consequences when these different timescales fall out of sync.

The challenge is to coordinate when we produce, convert, store, consume and invest in energy. Getting the timing wrong can make even the right technology or infrastructure investment an expensive mistake.

Why the energy transition depends on coordinating decisions from milliseconds to decades — and why the financial clock may be the most unforgiving of all.

Time has always fascinated me. Not so much the clock on the wall, which moves along at its usual predictable pace, but the way we experience time.

Some intense moments seem to last forever. A few seconds can feel like an eternity. And then you look up, twenty years have passed, and your children are leaving for college. Where did all that time go?

Albert Einstein showed us that time is relative, although his theory concerns something rather more sophisticated than our perception of a long Monday afternoon. His relativity involves motion, gravity and the physical nature of time. I’ll leave the mathematics to the physicists.

Still, I find the analogy useful, particularly when looking at the energy industry.

For a grid operator, a second can be critical. For an electricity trader, fifteen minutes can make the difference between a profit and a loss. For an industrial company, tomorrow’s production schedule determines when energy is needed. A cold winter can challenge an entire energy system.

And for an investor financing new energy infrastructure, ten years can be remarkably short.

These are very different clocks operating within the same energy system. What interests me is how often we manage them separately, even though the consequences are closely connected.

We discuss the energy transition in terms of megawatts, storage capacity, kilometres of electricity cables and billions of euros in investment. All perfectly relevant. Yet we seem to pay less attention to another question: when does all that capacity need to be available, and what happens financially if we get the timing wrong?

Electricity is perhaps the clearest example of the importance of time. It must be balanced continuously, and its market value can change within minutes. But the underlying challenge extends much further, to heating, industrial energy consumption, seasonal storage, the conversion between different forms of energy and the financing of infrastructure over decades.

I suspect this question of timing deserves a much more prominent place in energy strategy.

The value of electricity depends on when you need it

Electricity has an inconvenient characteristic: supply and demand must remain in balance continuously.

Frequency control operates in milliseconds and seconds. Other balancing mechanisms work over minutes. Electricity traders adjust their positions as forecasts change, while electricity suppliers and industrial customers prepare their consumption and production schedules for the following day.

On 30 September 2025, the European single day-ahead electricity market moved to 15-minute trading intervals for delivery from 1 October. This was more than an administrative change. It reflected the need for market schedules to follow increasingly variable electricity production and consumption.

With more wind and solar power, knowing how much electricity will be available is no longer enough. We need to know when it will be available.

A sunny afternoon may produce plenty of electricity precisely when demand is relatively low. A few hours later, when people return home and start cooking, charging their cars or heating their homes, the situation can look quite different.

The electricity produced at midday and the electricity needed in the evening may have significantly different economic values.

This is where batteries, flexible industrial processes, electric vehicles and energy management systems become interesting.

A battery is not particularly clever because it stores electricity. Its value lies in being able to deliver that electricity at a more useful moment, provided the difference in value covers the costs of doing so.

Greece provided a recent example.

An analysis published by The Green Tank in July 2026 examined the first three months of grid-scale battery operation in the Greek electricity market. Between April and June, the batteries purchased approximately €539,000 worth of electricity for charging and generated around €4.2 million in electricity sales revenue.

These figures are not net profits. They exclude investment, operating and other costs. But they demonstrate the economic potential of buying and selling electricity at different moments.

The analysis also estimated that the batteries prevented approximately 26.7 GWh of renewable electricity curtailment during those three months.

The batteries did not create more sunshine. They helped make better use of electricity that was already being produced.

Source: The Green Tank, July 2026

Moving energy through time has its limits

Managing electricity over a few hours is useful. But energy systems operate on many longer timescales.

Industrial production can sometimes be moved between day and night shifts. Charging electric vehicle fleets might be scheduled around cheaper electricity or available network capacity. A factory could adjust part of its production between weekdays and weekends.

These decisions are often described as load shifting, demand response or flexibility. The terminology varies, but the underlying principle is straightforward: move consumption or production to a more suitable moment.

Unfortunately, not all demand is equally flexible.

A hospital cannot postpone electricity consumption until tomorrow. Certain industrial processes need continuous energy. And moving an electric vehicle’s charging session by two hours will not solve a prolonged shortage of electricity during a cold, windless week.

South Australia demonstrated some of these limitations in June 2026.

During two days of tight electricity supply, cold weather increased demand while wind generation was exceptionally low. Batteries initially contributed, but their remaining charge progressively declined. Network limitations and market bidding behaviour added to the pressure, contributing to extreme wholesale electricity prices.

The Australian Energy Regulator’s subsequent analysis makes an important point: the availability of battery power does not guarantee that sufficient stored energy remains available throughout a prolonged difficult period.

Source: Australian Energy Regulator, August 2026

This illustrates a distinction that is sometimes lost in the enthusiasm for energy storage.

Power capacity tells us how much energy a system can deliver per unit of time. Energy capacity tells us how much it can deliver in total.

A battery capable of supplying a large amount of electricity for two hours does not automatically solve a shortage that lasts for two days.

Flexibility must therefore be evaluated against the duration of the problem it is supposed to solve.

And even when operational flexibility works perfectly, we still have to deal with seasonal variations.

From summer electricity to winter heating

The importance of timing becomes even clearer when we look beyond electricity.

Heat demand follows different patterns from electricity demand. In many European countries, demand for heating is concentrated in the colder months, while renewable electricity production can be abundant during periods when heating demand is low.

This creates an interesting opportunity.

What if we could use electricity or recover otherwise wasted industrial heat when it is available and store the resulting thermal energy until it is needed?

District heating networks can do precisely that, although the scale and economics depend heavily on the available heat sources, storage technology and local infrastructure.

Unlike a battery that stores electrical energy for a few hours, seasonal thermal storage can retain heat for much longer periods. It can help separate the timing of energy production from the timing of heat consumption.

Finland: storing summer heat for winter

In Vantaa, Finland, energy company Vantaan Energia is developing Varanto, a large underground seasonal thermal energy storage facility.

The project involves excavating three enormous caverns in the bedrock, which will eventually be filled with hot water.

When fully charged, the proposed installation will store approximately 90 GWh of thermal energy. According to the developer, that is enough heat to supply a medium-sized Finnish city for a year.

The facility is designed to store heat when suitable energy sources are available and release it through the district heating network when demand arises.

Construction is under way, with operation currently expected in 2030.

The estimated investment is approximately €300 million, including a €19 million investment grant awarded by Finland’s Ministry of Economic Affairs and Employment.

Source: Vantaan Energia — Varanto

I find this an interesting illustration because it connects several different timescales.

The heat may be produced during periods when energy is inexpensive or would otherwise go unused. It can be stored for months and consumed during the heating season. The infrastructure itself requires years of development and substantial capital investment, with the economic benefits expected over a much longer operating lifetime.

Varanto is still a project under development, not proof that seasonal storage of this scale will always be economically successful.

And the 90 GWh figure represents thermal energy, not electricity that can simply be returned to the power grid. The two forms of storage serve different purposes.

Nevertheless, the project demonstrates why the energy transition must be considered as an integrated system rather than a collection of separate electricity, gas and heating projects.

The value of an energy resource depends on its availability, its possible conversion into another form, the ability to store it and the moment at which it can be used.

Each conversion and storage step introduces costs, efficiency losses and technical limitations. But it may also create value by allowing energy produced at one moment to satisfy demand at another.

Sometimes the opportunity is measured in minutes. Sometimes in months.

And sometimes the timing problem is not about storing energy at all, but about building the infrastructure required to deliver it.

When infrastructure arrives too late

An electricity network may take years to plan, permit, finance and construct. The industrial facility or renewable electricity project that depends on it may be ready much sooner.

According to the International Energy Agency’s Electricity 2026 report, developing new grid infrastructure can take approximately five to fifteen years. New data centres may take only one to three years, while renewable generation projects can also be developed considerably faster than the networks needed to accommodate them.

This mismatch is already having financial consequences.

In September 2026, the UK’s National Audit Office published a report on delays to electricity transmission upgrades.

It found that grid constraint costs reached £1.9 billion in the 2025–26 financial year.

These costs occur when electricity cannot be transported efficiently from where it is generated to where it is needed. The system operator must intervene, for example by reducing production at wind farms in one area while increasing generation elsewhere.

The report warned that annual constraint costs could rise to £7.8 billion by 2030 without sufficient action to address the problem. This is a conditional projection, not an observed cost.

Meanwhile, Ofgem estimates that approximately £70 billion must be invested in Britain’s transmission network between 2025 and 2031.

Source: UK National Audit Office, September 2026

Consider what is happening here.

Substantial amounts of money have already been invested in electricity generation. The electricity is available, but part of the network cannot transport it to the places where it is needed. Additional money must then be spent operating around that limitation.

Of course, network constraints have several causes. Geography, changing generation patterns, insufficient capacity, planning delays and physical limitations all contribute.

But the timing mismatch is hard to ignore. Generation can become operational years before the transmission network is ready.

This is an expensive way to discover that infrastructure planning and energy production have been following different schedules.

It also reveals an uncomfortable investment dilemma.

Build the network too late and we pay for congestion, curtailed generation and delayed economic activity. Build it unnecessarily early and we risk tying up substantial capital in assets that are not yet fully used.

Neither outcome is particularly attractive.

The financial clock starts before the energy flows

For me, this is where the discussion becomes especially interesting.

The energy transition is often presented as an engineering and technology challenge. We need more renewable generation, additional storage, stronger networks, heating infrastructure and intelligent systems to coordinate everything.

All true. But underneath those technical requirements lies an enormous capital allocation problem.

Energy infrastructure typically requires substantial investment upfront, while its economic benefits are expected to materialise over decades.

Money is committed during development, permitting, procurement and construction. Financing costs accumulate. But revenue, regulated cost recovery and wider economic benefits may begin at different stages, depending on the type of project.

That makes timing an important component of financial viability.

Consider a deliberately simplified example.

Imagine a privately financed energy project requiring €100 million of capital, committed today. Once operational, it is expected to generate €10 million in annual net cash flow for twenty years.

Assume a discount rate of 6%.

If those cash flows start next year, their present value is approximately €115 million. Against the initial €100 million investment, the project has a positive net present value of around €15 million.

Now imagine the expected cash flows begin three years later, while the same capital remains committed today.

The discounted value of those cash flows falls to approximately €96 million.

A project with a positive net present value has become marginally negative, even though the technology, total future operating cash flows and expected operating lifetime remain unchanged.

The difference is approximately €18 million.

This is an illustration, not an actual project valuation. Real investments involve staged construction spending, financing structures, taxes, additional costs, contractual obligations and potentially different revenue arrangements. A delayed project might also defer some of its expenditure.

Nevertheless, the mechanism matters.

The timing of capital commitments and future cash flows can change whether an investment makes financial sense.

The example is particularly relevant for privately financed energy projects. Regulated electricity networks operate under different financial arrangements, with investment approval, depreciation, allowed returns and tariff recovery affecting how costs are allocated over time.

But the wider question remains: who finances capacity before it is needed, and who carries the risk if demand arrives later than expected?

Hornsea 4: when the financial assumptions no longer work

Ørsted’s Hornsea 4 offshore wind project provides a real-world example of how investment conditions can change during development.

The planned 2,400 MW project received a Contract for Difference award in September 2024.

Less than a year later, in May 2025, Ørsted announced that it would discontinue development in its existing form.

The company cited a combination of increasing supply-chain costs, higher interest rates and greater construction and operational risks associated with delivering the project according to its planned schedule.

Together, these developments had undermined its expected value.

Ørsted subsequently retained important development rights and permits and began exploring a reconfigured project for potential future development.

Source: Ørsted, May 2025

It would be incorrect to claim that timing alone caused the decision. Higher costs and broader project risks were also material.

But the case demonstrates how strongly the economics of capital-intensive energy projects depend on the conditions under which they are developed and financed.

The technical ability to construct an offshore wind farm does not guarantee that it will remain financially viable.

That distinction matters. A project can still be strategically desirable while its original investment case is no longer sufficiently attractive to justify committing more capital.

And postponing the decision is not necessarily free either.

Investing before demand exists

For energy infrastructure operators, the financial dilemma can become even more complicated.

An investment may be necessary long before the demand that justifies it has fully materialised.

Consider an industrial region preparing for major electrification. Several factories plan to replace fossil-fuel processes with electric alternatives. Perhaps a new data centre, hydrogen installation or district heating network is being considered as well.

The parties involved expect additional infrastructure to be required. But the exact timing and scale of future demand remain uncertain.

Waiting until all investments are confirmed may mean starting construction far too late. Building everything immediately risks creating capacity that remains underused for years, with costs ultimately borne by investors, customers or society.

The European Commission addressed this issue in its June 2025 guidance on anticipatory grid investments.

The guidance recognises that electricity network development cannot always wait for confirmed connection requests. It also emphasises the importance of managing uncertainty about future asset utilisation and allocating financial risks appropriately.

Source: European Commission, June 2025

The problem is not solved by simply telling network operators to invest earlier.

Earlier investment may require earlier financing, regulatory approval and arrangements for recovering costs. And when expected demand does not arrive, someone must bear the consequences.

The question is therefore not whether we should always build sooner or wait longer.

It is how to make credible investment decisions under uncertainty, while recognising that the cost of waiting can be substantial.

The Netherlands: €235 billion and some difficult choices

The Netherlands provides a useful illustration of the scale involved.

The 2026 Financial Impact of Energy Policy for Network Operators study, FIEN26, estimates that Dutch energy network operators will need to make approximately €235 billion in net energy infrastructure investments between 2026 and 2040.

These investments cover electricity, gas, heat and hydrogen infrastructure, with electricity accounting for the largest share.

The same study identifies potential reductions of approximately €9 billion to €33 billion in required investment in onshore electricity networks through more efficient network utilisation and different energy-system choices.

An important qualification: these are estimates of gross potential investment reductions, not guaranteed net savings. The study explicitly excludes payments for flexibility from that calculation. Whether a particular measure delivers a positive economic return depends on its implementation costs, reliability and actual impact on future network requirements.

Source: Netbeheer Nederland, FIEN26, March 2026

Even with those qualifications, the magnitude is worth considering.

We often discuss flexibility in terms of reducing electricity bills or shifting consumption from expensive to cheaper hours.

But flexibility can have another, potentially more important financial effect.

If industrial demand, charging infrastructure or distributed generation can be coordinated to reduce simultaneous peak loads, some network reinforcements may be postponed, resized or occasionally avoided.

The same applies to choices about how energy is supplied.

A district heating network, for example, may reduce the electricity required for individual heating systems in a particular area, depending on its heat sources and design. Conversely, a district heating system using large electric heat pumps or electric boilers may introduce substantial new electricity demand, while also offering opportunities for flexible operation and thermal storage.

These choices connect the infrastructure requirements of electricity and heat.

That is a very different business case from simply calculating the electricity saved or the trading revenue generated.

Instead, we should examine whether operational flexibility, energy conversion and storage can change future capital requirements across the energy system.

Of course, this only works when the flexibility is sufficiently reliable, available when needed and economically justified over the relevant period.

A factory promising to reduce electricity consumption during peak hours is one thing. A network investment relying on that factory’s continued flexibility for the next twenty years is another.

Long-term contractual certainty, technical reliability and the possibility of changing industrial activity become part of the investment decision.

There is also a limit to what smarter operation can achieve.

Digital systems cannot create unlimited physical network capacity. If energy demand continues to grow, substantial new infrastructure will still be needed.

In some circumstances, building ahead of demand will be the most sensible option, particularly where construction lead times are long and the economic consequences of delayed connections are severe.

The aim should not be to minimise infrastructure investment at all costs. It should be to make the right investments at the right time, taking both their direct financial costs and wider economic consequences into account.

Different clocks, different responsibilities

A timing test before committing to energy infrastructure

Before committing to a grid, storage or heat investment, I would examine four clocks together: the response time the system needs, when and for how long the energy is available, when the required infrastructure can be delivered, and when financing starts to carry a cost. For each, document the main uncertainty and test at least one delay scenario. A technically sound investment can still underperform if those clocks diverge. This also explains why local flexibility that grid operators cannot see and energy data that arrives too late to act upon can undermine an otherwise promising solution.

I see another challenge here, beyond engineering and finance.

The different timescales of the energy system are often managed by different people, departments and organisations.

An electricity trading team optimises tomorrow’s market position. An energy management system adjusts consumption every few minutes. An operations manager plans next week’s production. A district heating operator prepares for winter demand. An asset manager schedules maintenance and replacement over many years.

Meanwhile, an investment committee decides whether infrastructure costing hundreds of millions of euros should be financed today against demand projections extending decades into the future.

Each group may be making perfectly reasonable decisions within its own responsibilities.

Yet those decisions do not automatically produce the best result for the energy system as a whole.

Trading optimisation may favour one operating pattern while network constraints suggest another. Industrial customers may want connection certainty earlier than network operators can provide it. A heating network may benefit from electricity production that would otherwise be curtailed, but only if the necessary conversion and storage infrastructure exists.

Investors may require financial commitments that customers are reluctant to make before they know when capacity will be available.

The difficulty is not necessarily a lack of information. It is that the participants operate with different incentives, planning horizons and responsibilities.

Better forecasting, real-time data, energy management systems and digital twins can help connect these decisions.

But technology alone will not resolve the financial and organisational questions.

Someone still has to decide which capacity is needed, when it must be delivered, how uncertainty will be managed and who carries the costs when expectations turn out to be wrong.

That requires closer coordination between operational planning, infrastructure development, regulation and investment decisions.

For energy leaders, I would argue that time should become an explicit dimension of strategy and financial planning.

A serious investment assessment should examine not only the expected cost and capacity of an asset, but also what happens when commissioning, demand growth or revenue begins several years earlier or later than planned.

It should compare physical expansion with credible flexibility alternatives, considering their cost, reliability and duration. And it should make explicit which risks are carried by investors, customers, network operators and society.

This is not a plea for another dashboard. We already have quite a few of those.

It is about connecting decisions that have traditionally been made on different clocks.

The price of getting time wrong

Einstein’s theory of relativity is considerably more complicated than anything I have discussed here. But his work offers a useful reminder that time deserves more attention than we usually give it.

In the energy industry, time appears in different forms.

There is the need to balance electricity within seconds. The ability to move consumption between hours or days. The challenge of planning heat and energy availability across seasons. The years required to build infrastructure. And the decades over which investments must deliver sufficient value to justify their costs.

These timescales are connected, but they cannot all be managed in the same way.

We cannot solve every network constraint by shifting demand. Nor can we build our way out of every problem without considering the enormous amounts of capital involved.

What we can do is become more deliberate about the relationships between operational decisions, energy conversion, infrastructure planning and financing.

I would like to see investment decisions tested more systematically against different timing scenarios. Not merely what happens if costs rise by 10%, but what happens if the demand arrives three years early, the infrastructure arrives five years late or the flexibility we expected is no longer available.

And what happens if changes in electricity and heat demand make a different energy infrastructure investment more attractive than the one originally planned?

Those scenarios reveal risks that a conventional capacity forecast or a single financial projection may overlook.

The energy transition will require the right technologies, the right infrastructure and substantial financial resources. I have little doubt about that.

But I am increasingly convinced that coordinating when we produce, convert, store, consume and invest in energy will be just as important as deciding how much capacity we need.

Because an investment can be technically correct, strategically necessary and financially sensible on paper — and still deliver a disappointing result when the timing is wrong.

And unlike those twenty years that seem to disappear while your children grow up, the financial consequences of getting time wrong rarely disappear with them.